The school plans to relocate onto our new land are all on track.

It has been a very busy period finalising and lodging the water/sewerage/plumbing plans. Silver Tree will be at the forefront of environmental sustainability providing our own water and using grey water to reticulate the proposed orchard. Getting approval for these systems has taken much planning and discussion with the shire and now we are awaiting the state health department to sign off. Thank you to the relocation committee members for the work that has been done.

With the buildings being constructed over the next month and site works taking place, including driveways, pads and trenching work for services, a physical change to the land is imminent. Once these works are complete, a landscaping plan will need to be put into practice and this will require much community support. At this stage it is hoped all classes can move into the new buildings by the beginning of Term 3.